Delays Cost Nova Scotia $200 Million

Halifax Examiner reports on December 29th, 2021

Delays in Muskrat Falls project have cost Nova Scotia Power ratepayers $200 million

“Delays in the receipt of hydroelectricity from Muskrat Falls in Labrador have cost Nova Scotian ratepayers more than $200 million over four years to replace it with other sources of energy. That information was finally made public by Nova Scotia Power on Friday, December 24, after being ordered to disclose the amount by the regulator, the Utility and Review Board.”

Source: Halifax Examiner

Map of connections – Muskrat to Nova Scotia

various transmission components that connect Muskrat Falls to Nova Scotia. Graphic: Emera